Skip to main content

Weekly Reflection Day 6

This week we learned a lot about the right way to do things. On Monday when we began work we learned that many contractors don't put up strapping prior to sheetrock. This is due to the extra cost of putting it up. However by putting up the strapping it just adds more rigidity to the ceiling and should help stop it from sagging. However, when contractors do put up strapping they then according to the schools electrician run the wiring in between it. He says this is not good due to the fact that if some screws through the sheetrock later they could hit a wire. Due to this he instead drills through the joists to make a path for the wire up and out of the way. This will lead to a safer space down the road. We also learned about staining and applying urethane to the trim boards. This is a longer processes then many would think due to the time it takes to apply all the coats. These are important things to know just incase we do anything like this again. One other thing we learned is the map out where the lights are going in and make sure that they will throw off enough light. I did enjoy the work we have done so far. Insulation was a little bit of a drag. This is partly due to the full body suits we needed to put on to complete this job. However, putting up strapping was very fun and urethane and stain were the same. We were asked to complete all of these tasks to ensure it was done correct. Also due to proper planning by the people from maintenance everything has gone off without a hitch. The only thing that may not have been in the plan is we had to wait for urethane to dry. So during that time we helped fill some holes for the people at the ski area. This type of thing was not only fun but will benefit us. It is just like all we have done this week. Help us gain knowledge on many parts of the building process. Just this week we have done electrical, framing, carpentry, and landscaping. Which are great skills to have. All of this also help us achieve our goals of learning about building and helping plan the project and once completed it will give back to the community. That is a positive way to end a positive week.
Beginning of the week!


Middle of the week!

End of the week!

Comments

Popular posts from this blog

Day 2

Today when we showed up we started out by putting up strapping on the other half. After that, we cleaned up the job site and broke for lunch. For the afternoon session, we began staining wood. This wood will be used as trim once the sheetrock for the ceiling is up. The lights for the second half of the project also were being put in by the electrician. Tomorrow seems to be a day for insulation. The insulation will be the biggest part of the project and take many days.  Hours: 4:40 The project as it now stands.  The stained wood.  Kevin Nailing. 

Day 9

Today we started out by sheetrocking and got one more piece in. Then while Adam was cutting the next piece Kevin and I began scraping the mud off the first row. We finished that as the electrition showed up to cut out the first two lights in the first row. While he was doing that we began to apply the second coat of mud to the first row. After that, we broke for lunch. I was unable to make it back due to a race but Kevin and Adam got the rest of the sheets up this afternoon. Tomorrow we will begin mudding. Hours: 3:10 Total: 38:30 The mud all smoothed out! First two lights cut out!

Day 20

Today we showed up at the ski area to find the boards applied urethane on the day prior to be dry. This means that we were able to get an another coat on them and put up three more strips in the morning. We then went to lunch and when we got back we put up the remaining strips. This signifies our last day down at the ski area. I will miss doing this every day. Hours: 6:00 Total: 73:30 Midway! All Done!