Skip to main content

Day 10

When we showed up today the project was looking really good with all the lights cut out. I began by applying joint compound (mud) the second half of the ceiling while Kevin sanded. We also cleaned up the work space. Then Garry came by and told us to clean the surrounding walls to get the room ready to begin paint. We did that and then broke for lunch. After lunch, we continued to clean and prep for paint. We also cleaned the shop floor of urethane. Today was a good day.
Hours: 5:30
Total: 44:00
Second half with joint compound!

The first half sanded!

The first half when we left!

Comments

  1. Pictures look great! You guys have obviously done a ton of work, I am looking forward to seeing it again.

    ReplyDelete

Post a Comment

Popular posts from this blog

Day 2

Today when we showed up we started out by putting up strapping on the other half. After that, we cleaned up the job site and broke for lunch. For the afternoon session, we began staining wood. This wood will be used as trim once the sheetrock for the ceiling is up. The lights for the second half of the project also were being put in by the electrician. Tomorrow seems to be a day for insulation. The insulation will be the biggest part of the project and take many days.  Hours: 4:40 The project as it now stands.  The stained wood.  Kevin Nailing. 

Day 9

Today we started out by sheetrocking and got one more piece in. Then while Adam was cutting the next piece Kevin and I began scraping the mud off the first row. We finished that as the electrition showed up to cut out the first two lights in the first row. While he was doing that we began to apply the second coat of mud to the first row. After that, we broke for lunch. I was unable to make it back due to a race but Kevin and Adam got the rest of the sheets up this afternoon. Tomorrow we will begin mudding. Hours: 3:10 Total: 38:30 The mud all smoothed out! First two lights cut out!

Weekly Reflection Day 6

This week we learned a lot about the right way to do things. On Monday when we began work we learned that many contractors don't put up strapping prior to sheetrock. This is due to the extra cost of putting it up. However by putting up the strapping it just adds more rigidity to the ceiling and should help stop it from sagging. However, when contractors do put up strapping they then according to the schools electrician run the wiring in between it. He says this is not good due to the fact that if some screws through the sheetrock later they could hit a wire. Due to this he instead drills through the joists to make a path for the wire up and out of the way. This will lead to a safer space down the road. We also learned about staining and applying urethane to the trim boards. This is a longer processes then many would think due to the time it takes to apply all the coats. These are important things to know just incase we do anything like this again. One other thing we learned is the ...