Skip to main content

Day 12 Weekly Reflection

After this week our project is really starting to take shape. We were able to get up all the sheetrock, apply joint compound, and paint one side. By doing these things we were able to learn a lot about construction (mostly sheetrocking). We learned how to put up large 12-foot pieces of sheetrock with a drywall lift (the easy way). The key is to ensure that the first sheet it cut square because if it is not you will need to cut all the remaining pieces at an angle to line up with the first. When applying joint compound we were able to learn the importance of sanding and applying multiple coats. To ensure a perfectly smooth finish. When painting we learned you must have long and consistent strokes with little pressure. This ensures that the finished product is as consistent as possible. It was a fun week and one I truly enjoyed. The sheetrocking was really fun due to the fact it went quite fast and left a really good looking consistent. I really like how that went. We then moved on to applying joint compound which was also quite fun by nature of the work. The one part I did not like was sanding the joint compound off. That was a tough job and one entirely above the head. However, what came next was also fun. It was nice to get painting because of the finished product. I love looking back and being able to see what was done and have that satisfaction of another part of the job done. We were asked to do all of this due to the fact they all must be done to complete the job. There were very few surprises. However, there was one. After we finished the first row we forgot to cut out for one electrical line. However, the electrician was able to fix that by fishing for it and cutting out a hole after the fact. So the problem was easily fixed. We benefited from the knowledge of this mistake and all the other pieces of info we picked up throughout the week. It helped us achieve our goals of learning about construction and when completed will also benefit the community.



Beginning of the week!

Middle of the week!

End of the week!

Comments

Popular posts from this blog

Day 2

Today when we showed up we started out by putting up strapping on the other half. After that, we cleaned up the job site and broke for lunch. For the afternoon session, we began staining wood. This wood will be used as trim once the sheetrock for the ceiling is up. The lights for the second half of the project also were being put in by the electrician. Tomorrow seems to be a day for insulation. The insulation will be the biggest part of the project and take many days.  Hours: 4:40 The project as it now stands.  The stained wood.  Kevin Nailing. 

Day 11

As of tonight, I have completed 50 hours of senior project work (the requirement). However, even though our hours have been completed we still have tons of work ahead of us. Today we began by sanding the other half of the sheetrock. This is a physically exhausting job and is never that much fun but must get done. After that, we put the first coat of paint on the first side. It looked pretty good after. Then we broke for lunch. After lunch, to our surprise, the paint had dried enough for a second coat. On Monday we will continue to sand the second side. Hours: 6:00 Total: 50:00 One side sanded and one painted!  Sanded side! Painted side!

Day 9

Today we started out by sheetrocking and got one more piece in. Then while Adam was cutting the next piece Kevin and I began scraping the mud off the first row. We finished that as the electrition showed up to cut out the first two lights in the first row. While he was doing that we began to apply the second coat of mud to the first row. After that, we broke for lunch. I was unable to make it back due to a race but Kevin and Adam got the rest of the sheets up this afternoon. Tomorrow we will begin mudding. Hours: 3:10 Total: 38:30 The mud all smoothed out! First two lights cut out!