Skip to main content

Day 12 Weekly Reflection

After this week our project is really starting to take shape. We were able to get up all the sheetrock, apply joint compound, and paint one side. By doing these things we were able to learn a lot about construction (mostly sheetrocking). We learned how to put up large 12-foot pieces of sheetrock with a drywall lift (the easy way). The key is to ensure that the first sheet it cut square because if it is not you will need to cut all the remaining pieces at an angle to line up with the first. When applying joint compound we were able to learn the importance of sanding and applying multiple coats. To ensure a perfectly smooth finish. When painting we learned you must have long and consistent strokes with little pressure. This ensures that the finished product is as consistent as possible. It was a fun week and one I truly enjoyed. The sheetrocking was really fun due to the fact it went quite fast and left a really good looking consistent. I really like how that went. We then moved on to applying joint compound which was also quite fun by nature of the work. The one part I did not like was sanding the joint compound off. That was a tough job and one entirely above the head. However, what came next was also fun. It was nice to get painting because of the finished product. I love looking back and being able to see what was done and have that satisfaction of another part of the job done. We were asked to do all of this due to the fact they all must be done to complete the job. There were very few surprises. However, there was one. After we finished the first row we forgot to cut out for one electrical line. However, the electrician was able to fix that by fishing for it and cutting out a hole after the fact. So the problem was easily fixed. We benefited from the knowledge of this mistake and all the other pieces of info we picked up throughout the week. It helped us achieve our goals of learning about construction and when completed will also benefit the community.



Beginning of the week!

Middle of the week!

End of the week!

Comments

Popular posts from this blog

Day 10

When we showed up today the project was looking really good with all the lights cut out. I began by applying joint compound (mud) the second half of the ceiling while Kevin sanded. We also cleaned up the work space. Then Garry came by and told us to clean the surrounding walls to get the room ready to begin paint. We did that and then broke for lunch. After lunch, we continued to clean and prep for paint. We also cleaned the shop floor of urethane. Today was a good day. Hours: 5:30 Total: 44:00 Second half with joint compound! The first half sanded! The first half when we left!

Day 19

Today was a good day down at the ski area. We began the day by staining the pieces that would soon cover the beam. After that we began putting them up this took time to get them perfect. However, soon we were on to trim we got up the first row and soon realized we were short pieces. We went to the lumber yard to get more. We stained and applied the first coat of urethane to these boards.  They go up tomorrow. Time: 6:00 Total: 67:30 Trim up! Boards to case in beam! First board up!

Day 20

Today we showed up at the ski area to find the boards applied urethane on the day prior to be dry. This means that we were able to get an another coat on them and put up three more strips in the morning. We then went to lunch and when we got back we put up the remaining strips. This signifies our last day down at the ski area. I will miss doing this every day. Hours: 6:00 Total: 73:30 Midway! All Done!