Skip to main content

Day 8

Today was one of those days that we got a lot done. We began the day finishing off the insulation on either side of the ceiling. Then put up the final sheet in the third row. After that, we put hopefully the final coat of urethane on the boards. Soon after that we began and completed mudding the screw holes in the first row. After lunch Mike (the school's electrition) came by to finish up some work on the second row and get it ready for sheetrock. He also helped put up the first piece to ensure it was square. Tomorrow we will continue on the second row of sheet rock. Today was a busy day!
Hours: 6:00
Total: 35:20
The final piece on the first row in!

The screw holes filled! 

Kevin screwing in the first piece! 

Comments

Popular posts from this blog

Day 2

Today when we showed up we started out by putting up strapping on the other half. After that, we cleaned up the job site and broke for lunch. For the afternoon session, we began staining wood. This wood will be used as trim once the sheetrock for the ceiling is up. The lights for the second half of the project also were being put in by the electrician. Tomorrow seems to be a day for insulation. The insulation will be the biggest part of the project and take many days.  Hours: 4:40 The project as it now stands.  The stained wood.  Kevin Nailing. 

Day 9

Today we started out by sheetrocking and got one more piece in. Then while Adam was cutting the next piece Kevin and I began scraping the mud off the first row. We finished that as the electrition showed up to cut out the first two lights in the first row. While he was doing that we began to apply the second coat of mud to the first row. After that, we broke for lunch. I was unable to make it back due to a race but Kevin and Adam got the rest of the sheets up this afternoon. Tomorrow we will begin mudding. Hours: 3:10 Total: 38:30 The mud all smoothed out! First two lights cut out!

Day 10

When we showed up today the project was looking really good with all the lights cut out. I began by applying joint compound (mud) the second half of the ceiling while Kevin sanded. We also cleaned up the work space. Then Garry came by and told us to clean the surrounding walls to get the room ready to begin paint. We did that and then broke for lunch. After lunch, we continued to clean and prep for paint. We also cleaned the shop floor of urethane. Today was a good day. Hours: 5:30 Total: 44:00 Second half with joint compound! The first half sanded! The first half when we left!