Skip to main content

Day 14

Today we were surprised to find that the road had dried up down to the ski area. When we arrived the paint was dry and it was time for the trim. However, first, we had to clean up the mess from all the sanding and painting. So we did that and took the trash to the dumpster. Once we returned we began putting up some trim. However, we can't do it all and that is due to the fact we don't have the wood to put on in the beam yet. Due to that the rest of the trim must wait for that to arrive. So in the afternoon we continued cleaning all the cubies and had an early quitting time (1:30) due to that. Hopefully, the lumber will come in tomorrow.
Hours: 4:00
Total 59:00



The trim going up!

One side!

And the other!

Comments

Popular posts from this blog

Day 10

When we showed up today the project was looking really good with all the lights cut out. I began by applying joint compound (mud) the second half of the ceiling while Kevin sanded. We also cleaned up the work space. Then Garry came by and told us to clean the surrounding walls to get the room ready to begin paint. We did that and then broke for lunch. After lunch, we continued to clean and prep for paint. We also cleaned the shop floor of urethane. Today was a good day. Hours: 5:30 Total: 44:00 Second half with joint compound! The first half sanded! The first half when we left!

Day 2

Today when we showed up we started out by putting up strapping on the other half. After that, we cleaned up the job site and broke for lunch. For the afternoon session, we began staining wood. This wood will be used as trim once the sheetrock for the ceiling is up. The lights for the second half of the project also were being put in by the electrician. Tomorrow seems to be a day for insulation. The insulation will be the biggest part of the project and take many days.  Hours: 4:40 The project as it now stands.  The stained wood.  Kevin Nailing. 

Day 9

Today we started out by sheetrocking and got one more piece in. Then while Adam was cutting the next piece Kevin and I began scraping the mud off the first row. We finished that as the electrition showed up to cut out the first two lights in the first row. While he was doing that we began to apply the second coat of mud to the first row. After that, we broke for lunch. I was unable to make it back due to a race but Kevin and Adam got the rest of the sheets up this afternoon. Tomorrow we will begin mudding. Hours: 3:10 Total: 38:30 The mud all smoothed out! First two lights cut out!